Open
Task
It helps to automate the operations related to Tasks
of the Siebel CRM applicatio using the task name.
Using Open Task Activity
1. In
the Canvas
Tools pane, click Process
Components to expand the tool and view the
associated activities.
2. Drag
the Application activity and drop on to the Flowchart
designer
on the Canvas.
3. In
the Application Type list,
select WebApps.
4. In
the Select An Application
list, select the configured Siebel CRM application.

5. Double
click the Application
activity to open the activity block.
6. In
the Canvas Tools
pane, click Siebel
to expand the tool and view the associated activities.
7. Drag
the Open Task activity
and drop inside the Application
activity. The validation error symbol disappears when the required
inputs are provided.

8. In
the Task Name field, enter
the task name of the required Task.
NOTE:
|
To know the
task name, navigate to the required screen of the Siebel
CRM application manually and then access Site
Map > Administration
- Web Services. Search tasks
in the Find option,
and then copy the task name of the desired Task. |
The Open
Task activity is created.
You can use the WEB
MODE to configure the click action on the Next,
Previous and other buttons
of the displayed Task . See
the Web
Mode section to know how to configure the steps.
Open Task Activity Properties
The properties of the Open Task activity are listed
in the following table and can be edited in the Properties
grid on the right panel.
Property Name |
Usage |
Control Execution |
Ignore Error |
When this option is set to Yes,
the application ignores any error while executing the
activity.
If set to NA,
it bypasses the exception (if any) to let the automation
flow continue; however, it marks the automation status
as a failure, in case of an exception.
By default, this option is set to No. |
Delay |
Wait After |
Specify the time delay that must occur after the
activity is executed. The value must be in milliseconds. |
Wait Before |
Specify the time delay that must occur before
the activity is executed. The value must be in milliseconds. |
Misc |
Breakpoint |
Select this option to mark this activity as the pause
point while debugging the process. At this point, the
process freezes during execution allowing you to examine if
the process is functioning as expected.
In large or complex processes, breakpoints help in
identifying the error, if any. |
Commented |
Select this option to mark this activity as inactive
in the entire process. When an activity is commented,
it is ignored during the process execution. |
DisplayName |
The display name of the activity in the flowchart
designer. By default, the name is set as Open
Task. You can change the name as required. |
|
Application Activity
|